SVEL Group Delivered Substation for Miratorg’s Plant, in Bryansk

News

SVEL Group completed works contributing into power supply of Bryansky Broiler Plant, which is under construction by Miratorg Holding. SVEL specialists updated the design and working documentation, manufactured the equipment, delivered and assembled it in Bryansk, and then successfully commissioned the substation.

The scope of supply included the gas-insulated current transformers and circuit breakers, 16MVA/110kV oil-immersed transformer, and pre-fabricated switchgear building, along with the dry-type cast resin transformers for auxiliary purposes, oil-immersed voltage transformers and disconnectors. Disconnector is a new product for SVEL Group, which has successfully proven itself during operation at various industries. Since recently, tp order a disconnector by SVEL has become even simpler and more convenient, thanks to the configuration tool.

In addition to the key equipment, SVEL specialists managed to install 110kV twin-circuit transmission line up to Bryansk Plant. Construction activity to prepare foundations for the substation was completed by customer under supervision of SVEL engineers and the engaged design engineering organization.

SVEL Group has been cooperating with Miratorg Holding since 2018. During this time, we have supplied more than 60 dry-type cast resin transformers to the holding's plants in Pskov, Kursk, and Kaliningrad Regions, and one substation in Orel Region.