SVEL Group acted as the general contractor for the construction of the main step-down substation and overhead lines of the substation, carrying out construction and installation work at the facility.

About the project

About the project

Implementation of a project for a vegetable producer "Greenhouse" is an example of a complete turnkey solution.

The substation "Greenhouse" near the town of Stary Oskol was built for the needs of the agro-industrial enterprise of the same name - LLC "Greenhouse".

The greenhouse complex is intended for the cultivation of cucumbers and tomatoes using a special Dutch technology. The total area of ​​the farm is 108 hectares, and the volume of production is not less than 95 tons per year.

The customer needed to create a modern energy efficient substation to provide electricity to the areas of the new greenhouse facility.

SVEL Solution

SVEL Solution

SVEL Group acted as the general contractor for the construction of the main step-down substation and overhead lines, carrying out construction and installation work at the facility.

In addition, SVEL became a supplier of substation equipment. The delivery set included all products manufactured by SVEL, including oil and dry transformers, switchgear cells, reactors.

Thanks to the well-coordinated work of the SVEL team, the “Greenhouse” substation was launched in a short time - in just 6 months. Production of SVEL was approved by Sberbank for financing through leasing.